It is Friday evening at a machining plant in Chakan. The Level 3 file for a new steering bracket is finished: ballooned drawing, process FMEA, control plan, gauge studies, pages of dimensional readings. The quality head opens the last page, the one the customer’s engineer will read first, and finds the weight box empty and a drawing change level that does not match the purchase order. That page is the part submission warrant, and a thick, careful file can still come back for one blank box on it.
What is a part submission warrant for an auto component supplier?
A part submission warrant is the cover declaration of a Production Part Approval Process (PPAP) submission. PPAP is the method published by the Automotive Industry Action Group (AIAG) for showing a customer that your process makes parts that meet the drawing and specifications, at production rate, before you ship production volumes. The warrant is the page that ties every other element of that file to one part number, one drawing revision and one named signatory.
AIAG sells the manual under the product code PPAP-4, and Ford’s PPAP requirements that took effect on 15 June 2026 are still written for the fourth edition. The warrant is the last of the manual’s 18 elements. One tier-1, TI Fluid Systems, describes it in its supplier PPAP requirements as the approval sheet the supplier authorises, a summary that qualifies the part as ready for submission. Read it that way. Everything before it is evidence; the warrant is the claim.
For a tier-2 in Pune or Chennai, the warrant usually arrives through the tier-1 above you. One tier-1, Huf, publishes a customer-specific requirements document (revision 03, May 2025) that passes Ford’s requirements down to its own suppliers. It says Ford’s tier-1s must include the approved sub-tier part approval submissions with each phase of their own warrant to Ford. Your signature on a bracket for a tier-1 in Hosur can end up inside a file that goes to the vehicle maker.
European customers use a different name for the same job. Germany’s automotive association, the VDA, runs its own production process and product approval (PPA) procedure in Volume 2. The seventh edition, dated January 2026, maps its PPA report, which includes a self-assessment, to AIAG’s element 18, the warrant. The foreword says harmonising the two methods was discussed and that the German industry is open to one common approach in the long term.
Why the PSW matters when your customer works under IATF 16949
The warrant matters because it is the only page in the file where a named person at your company makes a written declaration. The AIAG form has you affirm that the samples are representative of your parts, that they were made by a process meeting the PPAP manual’s requirements, and that the evidence is on file and available for review. It also asks for the production rate the samples were made at, in parts over a stated number of hours. Every other element is data. The warrant is a commitment about that data.
Customers treat the PSW as one. TI Fluid Systems states that all fields must be completed before submission, that “NA” is acceptable in place of a blank, and that a blank field gets the entire PPAP rejected automatically. The same document says that when it signs a supplier’s warrant, the signature only means it has accepted the package; the supplier stays responsible for the content and accuracy.
The audit side works the same way. IATF 16949 is the quality management standard for automotive production, and the large OEMs publish customer-specific requirements to be used with it. Expect an auditor to read a signed warrant next to those requirements. The IATF Global Oversight customer-specific requirements page lists documents from Ford, GM, Stellantis, Volkswagen, BMW, Renault and others, including a separate Ford document for PPAP.
Indian OEMs do not appear on that page as of November 2026. For Tata Motors, Mahindra or Maruti Suzuki work, ask the customer’s supplier quality team for its current manual or portal instructions before you open the form.
We covered the paperwork load behind all this in why India’s auto-component boom needs shorter PPAP paperwork. A shorter file still ends on a warrant, and the warrant still has to be right.
How a part submission warrant works: nine blocks, field by field
The AIAG warrant falls into nine blocks. Customers issue it under their own form numbers, as Melecs does with its copy of the AIAG form and TI Fluid Systems does with its own PPAP warrant, but the blocks stay recognisable. Ford now treats an electronic PSW as its default route for production warrants, and the questions it asks are the same. Work through the blocks in this order.
- Part identity: part name, customer part number, your part number, the drawing number, its engineering change level and date, any additional engineering changes, the safety or government regulation box, the purchase order number, the weight and the checking aid details.
- Organisation manufacturing information: your supplier name and vendor code, and the address of the plant that made the parts.
- Customer submittal information: customer name and division, buyer and buyer code, and the application, meaning the vehicle or system.
- Materials reporting: whether customer-required substances of concern have been reported, whether through the International Material Data System (IMDS) or another format, and whether polymeric parts carry the right ISO marking codes.
- Reason for submission: at least one of ten boxes.
- Requested submission level: one of five levels.
- Submission results: which results are included and whether they meet all design record requirements, with an explanation required for any “no”.
- Declaration and signature: the affirmation, the production rate, any deviations, whether each customer tool is tagged and numbered, and the authorised signature with name, title, phone and email.
- Customer use only: the disposition (approved, rejected or other), the customer’s signature and an optional tracking number.
Keep the table below beside the person filling the form. The last column comes from the rejection causes we see most often in supplier files. It is our analysis, not an AIAG list.
| Block | Fields | What to write | Where it goes wrong |
|---|---|---|---|
| 1. Part identity | Part names and numbers, drawing number, change level and date, PO number | Exactly what the customer’s drawing and purchase order say | Change level on the warrant differs from the PO or the ballooned drawing |
| 1. Part identity | Weight (kg) | The customer’s stated rule; TI Fluid Systems asks for kilograms to four decimal places, averaged over 10 random parts | Rounded figure, grams, or one part weighed |
| 1. Part identity | Safety or government regulation | Yes or no, per the drawing and the customer’s instruction | Left blank because nobody knew |
| 2. Manufacturing information | Supplier name, vendor code, address | The plant that made the samples | Head office address used for a part made in a second plant |
| 3. Customer information | Customer, division, buyer code, application | Names as they appear in the customer’s portal | Buyer code missing or out of date |
| 4. Materials reporting | Substances of concern, IMDS, ISO marking | Yes, no or n/a; IMDS details where the form asks | IMDS submission not yet accepted when the warrant is signed |
| 5. Reason for submission | Ten boxes | Every reason that applies | Only “initial submission” ticked for a part that also changed sub-supplier |
| 6. Submission level | Levels 1 to 5 | The level the customer asked for | Level chosen by the supplier with no written request |
| 7. Results | Dimensional, material and functional, appearance, statistical | Ticks that match the documents actually in the file | “Meets all requirements: yes” with an open deviation |
| 8. Declaration | Production rate, tool tagging, signature | Parts and hours from the actual run, a named signatory | Rate copied from the quotation, not the run |
| 9. Customer use | Disposition and signature | Leave for the customer | Supplier fills it in or treats “other” as approval |
Three blocks need more than the table can hold. The first is weight. TI’s rule is in the table. Ford’s PPAP requirements add no rule of their own for part weight, so customers differ. Read yours first. A bracket that weighs 0.2 kilograms goes on the form as 0.2000 under TI’s rule, never as 200 grams.
The second is the reason for submission. The ten boxes are: initial submission; engineering change; tooling transfer, replacement, refurbishment or addition; correction of a discrepancy; tooling inactive for more than a year; change to optional construction or material; sub-supplier or material source change; change in part processing; parts produced at an additional location; and other. Tick every one that applies. A move of a die from Gurugram to a new plant in Sanand is both a tooling transfer and parts produced at an additional location.
The third is the level. Level 1 is the warrant alone, plus an appearance approval report for designated appearance items. Level 2 adds product samples and limited supporting data. Level 3 adds samples and complete supporting data. Level 4 is the warrant with whatever else the customer defines. Level 5 is the warrant with samples and complete data reviewed at your plant. TI Fluid Systems and a Standard Motor Products supplier manual both state Level 3 as the default, and TI Fluid Systems requires written authorisation before any exception.
Who signs the part submission warrant, and who should?
The form asks for an “organization authorized signature”, and the warrant should be signed by someone your customer has accepted as authorised to commit the plant. AIAG’s form does not name a job title. TI Fluid Systems only requires that an authorised person at the supplier approve the warrant before submission. The choice is yours. Make it once, write it into your quality procedure and tell the customer.
We compare the usual candidates against four criteria: does the person know the data, can they commit the production rate, will they answer the customer’s engineer within a day, and will the choice hold up when an IATF 16949 auditor asks who approved product release. The scores are our view from supplier files, not a rule from AIAG or any OEM.
| Signatory | Knows the data | Can commit the rate | Answers queries fast | Holds up at audit | Our verdict |
|---|---|---|---|---|---|
| PPAP or quality engineer who built the file | Yes | No | Yes | Weak unless named in the procedure | Prepares and initials, does not sign |
| Quality head or QA manager | Yes | Partly | Yes | Yes | The usual signatory for most plants |
| Plant head | Partly | Yes | Sometimes | Yes | Signs where rate and capacity are the customer’s main worry |
| Managing director or owner | Rarely | Yes | Rarely | Yes, but slows every submission | Only for small firms with no quality head |
On the customer side, someone from supplier quality signs the disposition box. At Ford, the authorised customer representative is the Supplier Technical Assistance site engineer assigned to your plant. The form offers three outcomes: approved, rejected and other. It does not define “other”. Ford’s requirements show what can sit between yes and no: an interim warrant approval needs an approved engineering or build deviation, and that deviation is the authorisation to ship. Ask for any “other” to be written out as a list of open points with dates. It is never a soft approval.
How to start: a first warrant in five working days
Start with the customer’s rules, then the documents, then the form. The order below works for a new part on a Level 3 request. In our experience it takes about a working week when the run-at-rate is already done.
- Read the customer’s requirements for PPAP. For Ford work through a tier-1, that is the Ford PPAP document and the tier-1’s own requirements. For an Indian OEM, ask for the supplier quality manual. Note the warrant format, the weight rule, the default level and any phase names.
- Check the drawing change level on the purchase order against the ballooned drawing and the dimensional report. All three must match before anything else is filled in. TI Fluid Systems says the submitted drawing revision must match the revision on the purchase order.
- Collect the run-at-rate record: parts made, hours run, production streams used. Ford’s phased PPAP, as Huf passes it down, starts with a Phase 0 run-at-rate and moves through quality, production and capacity verification, so the rate on the warrant has to come from a real run.
- Weigh the parts by the customer’s rule and write the average in the unit and format it asks for.
- Confirm the materials reporting. If you report through IMDS, AIAG’s errata sheet for the fourth edition asks for the module ID, the version and the date transmitted to the customer.
- Tick every reason for submission that applies and the level the customer asked for in writing.
- Fill every remaining field or write “NA”. Then the authorised signatory reads the whole file, not only the warrant, and signs.
Our PPAP documentation FAQ answers the questions that come up at each of these steps.
How to measure whether your warrants are working
Measure the PSW by what happens after you send it. Four numbers tell you most of what you need, and a spreadsheet is enough to track them.
First-pass approval rate = warrants approved on first submission ÷ warrants submitted in the period. This is the headline number. Track it by customer, because one customer’s rules may be the reason for most returns.
Submissions per part = total warrant submissions ÷ part numbers submitted. A part that needed three submissions cost you three rounds of the customer engineer’s attention. Find the parts above one and read the reasons.
Days to warrant = date signed warrant sent − date run-at-rate finished. This shows the paperwork lag. If the run is done and the warrant waits, the bottleneck is document preparation, not production.
Field errors by block = returns citing a block ÷ all returns. Use the nine blocks above as the categories. If most returns cite block 1, your problem is drawing control. If they cite block 4, it is materials reporting.
The warrant is the only page in a PPAP file where a named person puts their signature to the data.
What goes wrong with a PSW, and the early signs
Most PSW failures are visible before the file leaves the plant. The table pairs each common failure with an earlier signal and the fix. These are patterns from supplier files we have prepared and reviewed, and they are our analysis.
| Failure | Early signal | Fix |
|---|---|---|
| Change level mismatch | Engineering issues a revised drawing while sampling is under way | Freeze the revision in writing before the run and recheck the PO |
| Blank field | The form is filled by two people on different days | One owner per warrant, “NA” for every field that does not apply |
| Weight in the wrong format | Weight copied from the quotation or the drawing | Weigh the parts by the customer’s rule and keep the readings |
| Rate that the plant cannot hold | Run-at-rate done on a short shift with the best operator | Record the real run conditions and the number of production streams |
| Wrong reason for submission | A sub-supplier or plant change not logged in part history | Keep a change log per part and read it before ticking boxes |
| Materials reporting not accepted | IMDS entry sent the same day the warrant is signed | Send IMDS early and sign only after the customer accepts it |
| Sub-tier evidence missing | A bought-out part without its own approved warrant | Collect sub-tier approvals before your own file is closed |
The last row matters most for exporters. Huf’s version of Ford’s requirements says tier-1s must use a production part approval process with their own sub-tier suppliers and include those approvals with each phase of their warrant. A tier-2 in Chennai that cannot produce an approved warrant for a casting it buys becomes the reason a tier-1’s file waits.
A quieter failure is a correct PSW that its signatory never read. If the quality head signs thirty on the last day of the month, spread the signing out and have the signatory sample one supporting document per file.
When a full PSW is the wrong choice
A full Level 3 PSW is the wrong tool when the customer asked for something else. These are the common cases.
- The customer works to VDA Volume 2. A German customer may want the PPA report with its self-assessment. VDA’s own comparison maps that report to the AIAG warrant, but the form and the content differ, and the VDA dropped submission levels in its sixth edition in 2020. Ask which one before you start.
- The part is a service part. Ford’s requirements are written for use with both the PPAP fourth edition and a Service PPAP first edition. Use the service rules where they apply.
- It is an annual requalification. Huf’s document describes a Ford small PPAP every 12 months: a warrant, material certification not older than 12 months, and a full dimensional report on at least five parts, with a capability study for special characteristics. That is a warrant, but not a full Level 3 file.
- It is a prototype. TI Fluid Systems lists a prototype level defined by the customer or its own engineering team. A production warrant on a prototype part claims a process that does not exist yet.
In each case, get the customer’s instruction in writing. A level agreed on a phone call is hard to defend when the file is audited a year later.
There is also a case where a warrant should not be signed at all: when the results do not meet the design record and nobody has agreed a deviation. The form gives you a “no” box with a required explanation. Use it. A PSW that says “yes” with an open deviation turns a quality problem into a credibility problem.
People also ask
Who signs the part submission warrant?
An authorised person at the supplier signs the declaration, usually the quality head or QA manager named in your quality procedure. The customer’s representative then records approved, rejected or other in the customer-use box. As TI Fluid Systems puts it, the customer’s signature accepts the package; the supplier stays responsible for its accuracy.
Is a PSW required for every part number?
Usually, yes. TI Fluid Systems asks for a separate warrant for each part number unless it agrees otherwise, and a separate warrant for each set of tools or process used to make the part. Ford allows a family of parts on a single PSW only with prior concurrence from its site engineer. Check your customer’s requirements for the rule that applies to you.
What weight goes on a part submission warrant?
Use your customer’s rule. TI Fluid Systems asks for kilograms to four decimal places, averaged from 10 randomly selected parts with at least one from each tool or process. Keep the individual readings in the file.
What is the difference between a PSW and a VDA PPA report?
Both close an approval file with the supplier’s declaration. The PSW is AIAG’s element 18 with five submission levels. The VDA PPA report in Volume 2 includes a self-assessment, and the VDA’s seventh edition scopes the approval by product risk.