A press shop in Chakan gets the nomination for a seat-frame bracket on a new SUV. The purchase order is four lines long. The Tier-1’s supplier quality engineer sends a longer list the same week: a timing plan tied to the carmaker’s build events, a PFMEA, a pre-launch control plan, a gauge study and a trial run before any part ships. Nobody on the shop floor calls this APQP. It is APQP, and it looks much the same whether the part is a bracket, a die-cast housing or a machined shaft.
What does APQP look like on a real part?
Take the bracket. APQP, Advanced Product Quality Planning, splits the launch into five phases, and each one leaves a document behind that someone can check. The phase names and their standard outputs are listed in our APQP, PFMEA and Control Plan questions. On the shop floor they look like this.
- Plan and define. A kick-off meeting reads the drawing and the customer’s requirement documents line by line. The team writes down quality targets and a first list of special characteristics, such as the hole position that locates the seat. Someone builds the timing plan backwards from the PPAP due date and puts a name against every document.
- Product design. For a build-to-print supplier this phase is short. The design belongs to the customer, so the work is a feasibility review and a list of questions on tolerances the press cannot hold. Those questions are worth more now than after the die is cut.
- Process design. The process flow runs from coil to blanking, forming, welding and e-coat. The PFMEA scores what can go wrong at each step. The pre-launch control plan adds tighter checks for the first weeks of supply, when the process is new and the operators are still learning it.
- Validation. Gauges are built and studied for repeatability. A trial run at production rate feeds the capability studies. Then the production control plan and the PPAP go to the customer with sample parts.
- Feedback. After launch, line rejections and field returns come back into the PFMEA. The next bracket starts from a better file.
APQP is the same five phases on every part. The examples differ in where the risk sits.
Which launches trigger APQP, and what does each one produce?
The five phases stay the same. What changes from one example to the next is where the effort goes and what the customer asks to see at the gate.
| Example | Where most of the APQP work sits | What the customer checks at the gate |
|---|---|---|
| New stamped or machined part, build to print | Process design and validation | Process flow, PFMEA, control plan, gauge study, capability results, PPAP |
| New part with design responsibility | Product design, then process design | DFMEA, design reviews, drawings, then the full process file |
| Part with a bought-out casting, forging or plating | Sub-tier readiness alongside your own plan | Evidence that the sub-tier part is approved and its critical controls work |
| Change to tooling, process, material or sub-supplier | A shortened loop through phases 3 and 4 | Change approval, updated PFMEA and control plan, fresh samples |
| Capacity increase on an approved part | Validation at the new rate | Capacity evidence and a run at the new volume |
The first row is the bracket above. The second row adds design work on top: a DFMEA, design reviews and a verification test plan. Ford, for example, wants written approval from its product engineers on the design verification and production validation reports for the first sample parts. A build-to-print supplier skips most of that, though Ford still expects it to collect the DFMEA information and the potential critical and significant characteristics from Ford before writing the PFMEA.
The last three rows are where suppliers tend to under-plan, because none of them feels like a new launch. The next three sections take them one at a time.
How does APQP work when a casting or plating step is bought out?
Picture a machining shop in Hosur that supplies an aluminium housing. The raw casting comes from a foundry and the anodising from a job shop down the road. The machining shop’s own PFMEA can be perfect and the housing can still fail on porosity, which was decided in the foundry weeks earlier.
APQP for this part means two plans running side by side. Your timing plan carries a row for each bought-out source with its sample date and approval date. Your process flow starts at receiving inspection. Your control plan says which casting characteristics you measure yourself and which you accept on the foundry’s certificate.
Ford’s requirements show how far a carmaker can push this. Its Tier-1 suppliers must require their sub-tier suppliers to use APQP and must run a part approval process for them. The approved sub-tier submissions go to Ford with each phase of the warrant. Where a critical characteristic is controlled at the sub-tier, the PPAP package has to show that those controls stop non-conforming parts from shipping. If you are the foundry in this picture, expect your customer to ask for a small APQP file of your own.
What does APQP look like for a tooling or process change?
Eighteen months after launch, the forming die on the bracket cracks. The plant decides to move the job to a larger press with a new die. The part number has not changed and the drawing has not changed, so the temptation is to make the switch and tidy up the paperwork later.
That order is the wrong way round. Ford’s document says a PPAP submission is required for any change in the manufacturing process after approval and for any additional or modified production tooling or equipment. It also requires approval through its Supplier Request for Engineering Approval process before a supplier-initiated or sub-tier change is implemented. Other customers word it differently, but most want to hear about the change before it happens.
Once the request is approved, the loop is short. Update the process flow and the PFMEA lines for the operations that moved. Revise the control plan. Re-study a gauge only if the measurement method changed. Run the new tool at rate, repeat the capability study on the special characteristics, and submit fresh samples with a new warrant. A plant with a tidy original file does far less work here than at the first launch, because most pages carry over untouched. A plant that changes first and asks later pays in rupees and weeks: a second trial run, re-made samples, and a customer who now reads every later submission twice.
What changes when the customer raises volumes on an approved part?
The SUV sells better than planned and the schedule goes up. Nothing about the part is new, yet the approval you hold was given for a stated capacity. Ford lists a revised required capacity that exceeds the supplier’s verified capacity among the events that need a PPAP submission, and it asks for evidence from a capacity analysis report behind the capacity figures on the warrant.
How much APQP work this means depends on how you find the extra parts. A third shift on the same line is mostly a people question: operator training records, work instructions, and a run at the new rate. A second press line is a second process as far as the file is concerned. It needs its own trial run and capability study, and the control plan has to confirm that both lines use the same gauges and the same reaction plans. Ford goes further and asks for additional production validation testing when extra production streams are added to meet capacity.
How do customer requirements change the APQP file?
APQP is an industry method. No government regulator writes it. The rulebook comes from AIAG, which publishes the manuals, from IATF 16949, the standard certified suppliers are audited against, and from each carmaker’s customer-specific requirements. Those requirements force visible decisions in the file. Ford’s PPAP requirements, effective 15 June 2026, are a clear case, and you can read them in the Ford requirements document.
- The edition on page one. AIAG states that the APQP 3rd edition and the Control Plan 1st edition were required by GM and Stellantis from 1 September 2024 and by Ford from 31 December 2024. The timing plan should name both editions and the customer document it follows.
- One numbering chain. Ford requires characteristic traceability from the DFMEA through the PFMEA to the control plan and the process instructions, recorded on its APQP/PPAP Evidence Workbook. Number each characteristic once and carry that number through all four documents.
- Gauges before capability. Ford wants measurement system analysis finished on every gauge before the capability study starts. It accepts a Gauge R&R below 10 percent of tolerance, rejects one above 30 percent, and leaves the range in between to its site engineer. A variable gauge study should use at least 10 parts, 3 operators and 3 trials. That fixes the order of work in phase 4: gauge study first, capability study second.
- A capability number, stated in advance. Ford’s acceptance level for both initial and final process capability is a Ppk of at least 1.67, from a study of at least 25 subgroups of 5 parts, 125 measurements in all. Until the plant has that data, Ford asks for 100 percent inspection or mistake proofing built into the process. Write the target into the pre-launch control plan so nobody argues about it after the trial run.
- A sub-tier column. Ford’s Tier-1s track sub-tier readiness against its APQP/PPAP Readiness Assessment, known as Schedule A, and include the final Schedule A with the warrant. If you buy castings or plating, your plan needs a row for each source.
- Change approval before the change. The tooling example above starts with the approval request. The new die comes second.
Ford is one customer. An Indian Tier-1 supplying a domestic carmaker may meet different forms and different thresholds, and the habit that transfers is asking for the customer’s current document and reading it before the kick-off.
What did the APQP 3rd edition change for these examples?
AIAG says the 3rd edition adds sections on sourcing, change management, APQP programme metrics, risk assessment mitigation plans and gated management. The control plan content moved out into a standalone manual, the Control Plan 1st edition, which AIAG says adds a Safe Launch requirement to the control plan phases.
Read against the examples in the table, the new sections are familiar. Sourcing is the bought-out casting. Change management is the cracked die. Gated management is the rule that a phase does not close until its deliverables are reviewed and signed, which for a small supplier can be a one-page checklist with signatures from quality, production and the plant head. Safe launch, as most customers use the term, is the pre-launch control plan from the bracket example with a name on it: extra checks during early supply and a stated point at which they come off. Ask your customer what it expects there, because AIAG’s public summary does not list the checks.
Where do APQP files go wrong in practice?
Weak APQP files tend to share a few habits, and none of them is about statistics.
- The PFMEA is written after the trial run. It then describes the process that happened to work and misses the failure modes nobody saw that day. Draft it when the process flow is drafted, and revise it after the run.
- The control plan is copied from the last part. The frequencies and gauges match the old job. A reviewer finds a check listed for a feature this part does not have.
- The timing plan stops at kick-off. It is made once, filed, and never updated, so the gate review has nothing to be read against.
- Sample parts come from a hand-fed setup. Capability numbers from a handful of carefully made pieces say little about a full shift. Ford, for one, wants the capability data to cover the real production environment, including all tools, cavities and shifts.
What should a supplier decide before the first gate?
Three decisions save the most rework. First, confirm in writing which APQP edition and which requirement document your customer applies. The IATF publishes several carmakers’ documents on its customer-specific requirements page, including Ford, General Motors, Stellantis and Volkswagen, and a Tier-1 customer may add its own formats on top. Second, decide which of the examples above you are in, since a change loop needs a smaller file than a new launch.
Third, decide who owns what. The plant owns the engineering: the trial run, the measurements, the capability studies and the signature on the warrant. Drafting the process flow, PFMEA, control plan and report formats can be shared. Our page on the AI PPAP generator explains which parts of that drafting software can take on and which stay with your quality team.
People also ask
Is APQP only for new parts?
No. A change to tooling, process, material, location or sub-supplier usually runs a shorter loop through process design and validation. Most customers expect notification or approval first and fresh PPAP evidence afterwards.
Does a build-to-print Tier-2 supplier still do APQP?
Usually, yes. The design phase is thin because the drawing belongs to the customer, but the process flow, PFMEA, control plan, gauge studies and trial run are still yours. Ford, for one, requires its Tier-1s to make sub-tier suppliers use APQP.
Where does an APQP file usually start?
With the kick-off and the timing plan. The timing plan lists each deliverable against the customer’s gate dates, and later status reports are read against it, so it sets the pace for every other document.